Three Quebec installers review 8 months of Hydro-Québec solar subsidies.
Eight months after Hydro-Québec launched its solar subsidies, what has really changed on the ground? To find out, Floréal Villanova brought together three installers from three regions of Quebec: Sébastien Muniz (SoluSolaire, Montreal area), David Le Breton (Darwin Solutions énergétiques, Quebec City area) and Frédéric Lavoie (Alt-Énergie, Lac-Saint-Jean).
A market shifting to grid-tied systems, more customers who are often less informed, connection delays that are hard to predict, municipal rules that change from one town to the next, finally solid returns, and a surprise for batteries on October 1. An honest, field-level review.
Sébastien Muniz runs SoluSolaire, which installs grid-tied solar systems, often with batteries, in the greater Montreal area. Website: solusolaire.ca
David Le Breton founded Darwin Solutions énergétiques in Quebec City, specializing in commercial, industrial and agricultural solar. He previously worked at Opsun, a Quebec manufacturer of solar racking. Website: darwinse.com
Frédéric Lavoie represents Alt-Énergie, an Alma-based company long specialized in off-grid systems (forests, outfitters), which now mostly installs grid-tied residential and commercial systems across Quebec. Website: altenergie.ca
🎥 YouTube: here
🎧 Spotify: here
🍎 Apple Podcast: here
▶️ YouTube Music: here
According to Frédéric Lavoie of Alt-Énergie, it takes 45 to 60 days from first contact to commissioning when everything goes perfectly, but more often 3 to 6 months. When the subsidies launched in April, Hydro-Québec answered connection requests within days; installers now see about a month of waiting, and final authorization can take longer. Commercial projects over 100 kW follow a longer process.
It depends entirely on the municipality. Some require no permit, others limit how much of the roof can be covered or require a variance. In Montreal, rules vary by borough: Sébastien Muniz mentions Rosemont–La Petite-Patrie, which asks for engineering plans for a rooftop installation. Check local rules before starting the project.
The homeowner submits the application online, after Hydro-Québec's final connection authorization and no later than nine months after installation. The LogisVert program guide plans 10 to 12 weeks of processing after a complete application is received, and payment is sent by mail. Sébastien Muniz's first customer was paid in two months. The customer pays the full cost of the work first.
According to the guests, a residential project without a battery usually pays back in 8 to 12 years, and over 15 years on some small flat roofs. In commercial and agricultural projects, David Le Breton sees 5 to 7 years, depending on the electricity rate and thanks to tax advantages reserved for businesses: the federal Clean Technology Investment Tax Credit (30% if labour requirements are met, 20% otherwise) and the 100% first-year deduction for Class 43.1 equipment. Every project is different: talk to an accountant.
Yes, since October 1, 2026, through the Quebec government's Rénoclimat program, not Hydro-Québec: up to $4,000 for the battery and up to $1,000 for connection by a master electrician, for a maximum of $5,000. The measure is not retroactive and targets residential customers; nothing has been announced for commercial projects. Hydro-Québec's solar subsidy still excludes batteries.